39th Street Improvements, Noland to Crysler

View Map


Project Name: 39th Street Improvements, Noland to Crysler
Location: on 39th Street, from Noland Road west to Crysler Avenue

Description:
The 39th Street Improvements, Noland Road to Crysler Avenue improves 39th Street from the existing condition to a 3-lane street with curbs, sidewalks, new drive approaches and an improved storm sewer system. This project is being administered jointly with Jackson County Missouri.

Update: This project is now in the acquisition phase. Right-of-way and or easements will need to be obtained from seventy-six (76) property owners.

Start Date:
Summer 2010
Design: PARS Engineering
Contact Person: Ivan Ubben, 325-7768
Last Report Date: 08-21-09
Project Status: Acquisition