39th Street Improvements, Noland to Crysler

View Map


Project Name: 39th Street Improvements, Noland to Crysler
Location: on 39th Street, from Noland Road west to Crysler Avenue

Description:
The 39th Street Improvements, Noland Road to Crysler Avenue improves 39th Street from the existing condition to a 3-lane street with curbs, sidewalks, new drive approaches and an improved storm sewer system. This project is being administered jointly with Jackson County Missouri.

Update: This project will advertise on Tuesday, June 1, 2010.  Bids will be opened Thursday, June 24, 2010 in conference room A at City Hall. 
 
View Invitation to Bid.
View plan holders list. 
View bid tabs.

Start Date:
Summer 2010
Durration: 270 Days
Contractor:
Contact Person: 
Shar Dilmaghani, 325-7611
Last Report Date: 07/08/10
Project Status: Pre-Construction